1、单选题:
The main objectives of project management are ( )
选项:
A:Time, cost, quality, and/or scope
B:Profitability, cost, time
C:Customer satisfaction, cost, time
D:Calendar dates, facilities available, funding
答案: 【Time, cost, quality, and/or scope】
2、单选题:
The person responsible for balance the time, cost and quality objectives to achieve project success is ( )
选项:
A:The line manager
B:The project manager
C:The Human Resources Department
D:The executive sponsor
答案: 【The project manager】
3、多选题:
The knowledge areas in PMBOK include: ( )
选项:
A:Risk management
B:Information management
C:Cost management
D:Scope management
答案: 【Risk management;
Cost management;
Scope management】
4、判断题:
The temporary nature of projects means that a project has a short duration. ( )
选项:
A:对
B:错
答案: 【错】
5、判断题:
There are five process groups in PMBOK.( )
选项:
A:错
B:对
答案: 【对】